FLOORING

To Ply squares over heated concrete sub-floor

step 1

Diamond grind floor to remove construction debris, high spots and to ensure the best possible key to the slab, Vacuum floor and apply vapour barrier. Prime and level low spots

step 2

Trowel adhesive on to the slab and fit accoustic underlay over

step 3

Trowel adhesive on to the underlay and fit 400 x 400mm ply squares over. Allow 2-3mm expansion gap between squares. Sand ply squares flat, if necessary

step 4

Trowel adhesive to top surface of ply and lay T&G over, secret fix with 40-45mm staples. Stagger all joins

step 5

Sand,trowel fill, fine sand and apply polyurethane coating (min, 3 coats of poly).